Upper Prosser Dam Scour Valve Replacement Project

What's this project all about?

The Upper Prosser Dam has a scour valve to release flows from storage. This valve is located over halfway along the dam wall and must be operated manually. The dam wall is accessed from the riverbed which has eroded over time and become steep and rocky. As a result of the increased safety risks, the dam storage is not currently being utilised.

The purpose of this project is to construct a new scour valve in a safe and accessible location. This will enable the use of the dam storage improving water security in the area and ensuring the safe operation of a critical asset.

For more information

If you have any questions or would like to know more about this project, please contact our Community and Stakeholder Engagement team, on 13 6992 or via email: enquiries@taswater.com.au

Project timeline

Site works commenced in May 2021 and are due to continue through to late September 2021. 

As the final works must be completed during summer, the site will demobilise in late September and remobilise in December 2021.

The project is scheduled for completion by January 2022.