Cambridge Road Water Main Renewal

What's this project all about?

The Cambridge Road Water Main Renewal is part of our commitment to delivering improved infrastructure and quality drinking water to the community of Bellerive.

This project will start mid-April 2023 and run for approximately 12 weeks.

The project will replace 572 meters of water main from Ormond Street to Cambridge Road and work will be completed with remediation of the road. This project is one of many being delivered by TasWater in the Bellerive Area.

What you can expect from our project team:

  • Regular communication and updates to keep you informed of our activities throughout the project.
  • Service interruptions will be communicated to businesses and residents by written notification.  We will speak with businesses directly to discuss your requirements.
  • Traffic management personnel will ensure you have safe and direct access to and from your property as traffic restrictions will apply.
  • Our commitment is to minimise any inconvenience during construction and keep machinery-related noise to a minimum in out of hours works.
20220829 Bellerive Works

Project timeline

This project commenced mid-April 2023 

Scheduled for completion in late August 2023.

Community newsletters

Have a question?

For the latest information about TasWater projects and news please visit our website regularly and follow us on social media:

Instagram @ TasWater (@tas_water)

Youtube @TasWater - YouTube

X @ TasWater (@Tas_Water)

If you would like to connect with one of our Community & Stakeholder Engagement team members about a project happening near you, please email [email protected] or call 13 6992.

Was this page useful?

Rate this page

  • Rate as Yes33.33% Yes votes
  • Rate as No66.67% No votes

Have your say